On 15 October 2026 will enter into force Law no. 169 of 29 September 2026 (the Delegation Law), published in Official Gazette no. 227 of 30 September 2026, regarding sustainable nuclear energy. The timing set for the adoption of one or more legislative decrees by the Italian Government is tight: by 15 October 2027 (i.e. within the next 12 months, with a possible 90-day extension). Corrective decrees may then be adopted within 24 months of each decree. The Ministry of Environment and Energy Security (MASE) aims to act even faster: implementing decrees by December 2026.
The Delegation Law sets general principles, not detailed rules. For investors and banks, the key question is whether the implementing decrees will create a framework that allows new-generation plants, especially small modular reactors (SMRs), to obtain financing.
Why financing is the real test (and not the technology)
The Delegation Law covers the whole nuclear life cycle: the national programme, the choice of sites, the construction and operation of new plants (also for hydrogen and heat production), fuel production and reprocessing, radioactive waste and spent fuel, the dismantling of plants and the new organisation of nuclear safety. It focuses on new-generation technologies such as SMRs and advanced modular reactors (AMRs) and, in the longer term, fusion.
Since the detailed rules are not yet written, the main question for investors is simple: can these projects be financed? For an SMR financed through project finance, this depends less on the technology than on how the risks of development, construction, operation and revenues are shared and reduced.
Ten factors banks will likely look at include the following:
- Technology risk: first plant or proven design
Banks distinguish between a first-of-a-kind (FOAK) plant, the first one built with a given design, and an Nth-of-a-kind (NOAK) plant, which uses a technology already built and in operation. A FOAK SMR has uncertain performance and costs and may need design changes or face permitting problems. For this reason, it is difficult to finance only through project finance. Banks would usually ask for very strong sponsors, government support, a high level of equity and possibly guarantees that the plant will be completed.
- Permits and nuclear regulation
For a nuclear plant, having all permits (for construction, operation, fuel, radioactive waste and dismantling) is a real condition for financing and banks will expect most permitting risk to be resolved before the financing is signed. The Delegation Law helps in two ways: it creates a single integrated permit issued by MASE and it allows the recognition of authorisations already issued in countries of the OECD Nuclear Energy Agency (OECD-NEA). But it sets no maximum time limit, so certainty on timing will depend on the implementing decrees.
So, which permits exactly? The integrated permit will cover the construction and operation of the plant and its connected works, replacing all other authorisations, licences and consents. It may also change local planning rules, declare the project urgent and of public utility and allow the expropriation of land. One important exception: the environmental assessments under Legislative Decree no. 152/2006, including the environmental impact assessment, stay outside and must be obtained separately.
- Construction risk
History is not on the side of big nuclear. Large nuclear projects have often suffered higher costs, delays of several years and claims from contractors. SMRs promise to change this story, because they are built in modules, largely in factories, using standard designs. Banks will still require a financially solid EPC contractor, a fixed completion date, performance guarantees, penalties for delay, direct agreements and the right for banks to take over the project if needed, as in any large energy project. The Delegation Law does not deal with how construction risk is shared, since this will be left to the contracts.
- Stable revenues and buyers of the energy
An SMR requires investments of billions of euros, therefore stable and predictable revenues are essential. The structures that banks find easiest to finance are: (i) a Regulated Asset Base (RAB) model, where consumers help pay for the plant during construction; (ii) a Contract for Difference (CfD), where a public authority guarantees the price; or (iii) a long-term power PPA backed by the State, with the State, a public utility or another highly rated buyer and PPAs with companies, for example to supply data centres, AI campuses or industrial areas. The Delegation Law allows for possible support measures and coordination with electricity market rules, but it does not choose a model. This is maybe the main open question.
- Government support
Today it is hard to imagine an SMR financed only by the market. Banks will normally look for a mix of State guarantees, support from export credit agencies, public grants, tax credits and guarantees on loans. The Delegation Law allows public support, but EU State aid rules will shape how it works. The law’s own funding is limited: EUR 20 million per year in 2027, 2028 and 2029 from MASE resources. Any decree that creates new public costs can only be adopted once the necessary funds are available.
- Fuel supply and waste management
Banks will check that fuel is available for the whole life of the plant, that there is no risky dependence on certain countries and what the rules and costs are for treating, storing and disposing of waste. The Delegation Law covers fuel production and reprocessing, as well as temporary storage and final disposal sites.
- Costs of dismantling the plant
Unlike solar or wind plants, a nuclear plant has very high costs at the end of its life for dismantling, cleaning up the site and disposing of waste. The Delegation Law requires adequate financial guarantees for the whole life cycle, paid only by the permit holder, including one or more funds for dismantling and waste costs. Banks will focus on separate funds, reserve accounts for dismantling costs and any public obligations for managing spent fuel.
- Insurance and nuclear liability
Clear rules are needed on civil liability for nuclear damage, liability limits, compulsory insurance and possible State support above certain amounts. The Delegation Law requires the operator to provide guarantees, financial cover and insurance, also for risks outside its control, but the detailed rules are still to come. The message is clear: without a clear nuclear liability regime, financing would be very difficult.
- Environmental, social and governance (ESG) risks and local acceptance
Nuclear is now partly included in the EU Taxonomy (the EU list of sustainable activities). However, local opposition, political risk, changes of government and court challenges remain important. Banks will want reassurance that political support will remain stable for the whole life of the project. They will also carry out detailed checks on compliance with the Taxonomy and with the “do no significant harm” (DNSH) principle, as well as on safety, supply chain, governance, relations with local communities and end-of-life management.
- Security for the banks
In a typical project finance structure, the security given to the banks would be similar to that of a large energy infrastructure project: a pledge over the shares of the project company (special purpose vehicle, SPV), transfer to the banks of the rights under the EPC contract and the PPA or CfD, security over bank accounts, transfer of the rights under insurance policies and direct agreements with the main counterparties.
Next steps
The implementing decrees will decide the issues that matter most for financing: the national programme, which technologies are allowed, how sites are chosen, the timing and steps of the permit process, how the integrated permit links with the environmental assessment, the roles of the State, Regions and local authorities, the structure of the safety authority, the financial guarantees required from operators, any public support and the waste management model. Sponsors, energy companies, EPC contractors and banks may want to use the coming months to assess their position and take part in the consultation on the implementing rules.