Introduction

How do you get major energy users, such as data centres, to contribute appropriately to the energy system of the future?

It is a complex quest. As we have reported on previously, electricity availability is increasingly a determining factor for the location and economics of data centre development. Access to high-capacity grid power, complemented by on-site generation (traditionally diesel, but increasingly storage and solar) is a non-negotiable for data centres.

While on the one hand data centres are great pioneer energy users that can underpin the build out of the grid for the benefit of a broader group of users, data centres also contribute to grid constraints and can create system risk. Unblocking those constraints requires a number of things, including:

  • Ensuring that upgrades are paid for the by right user: In the ordinary course, customer-specific connections are funded by the customer requiring the upgrade. However, trunk or shared upgrade infrastructure costs can still, sometimes, find their way onto the regulated asset base and so be recovered from the broader energy user base, contributing to rising power bills.
  • Ensuring sufficient power supply (through the right generation mix across renewables and firming): Power offtake agreements are required, in addition to power delivery through network infrastructure. Data centres (and their tenants) and other large loads are increasingly exploring sophisticated power procurement arrangements, inclusive of renewable power matching and direct hedge market participation. However, there is opportunity for new loads to more directly sponsor new generation build out.

On 5 August 2026, several policy and legislative initiatives were announced seeking to support these actions and imperatives.

Greening and firming energy supply

The Australian Energy Market Commission (AEMC) has provided advice to the Energy and Climate Change Ministerial Council (ECMC) on ways to amend existing laws to require data centres to fully offset electricity demand with new renewable generation and to demonstrate firmed capacity.  The AEMC has recommended the following:

  • Drive new renewable investment through the REGO scheme: Data centres would be mandated to offset consumption using certificates linked to new renewable generation under the Renewable Electricity Guarantee of Origin (REGO) scheme.

  • Introduce a data centre contract obligation for firming capacity: New data centres would be required to demonstrate to the Australian Energy Regulator that they have sufficient firm contracts to cover their load. This policy could be implemented through changes to replicate certain aspects of the existing Retailer Reliability Obligation architecture from the National Electricity Law, which currently applies to energy retailers.

  • Introduce market registration requirements for data centres (or inverter-based loads): Data centres (or inverter-based loads) above a defined threshold would be required to register with Australian Energy Market Operator (AEMO). It would also provide increased visibility of data centre load in the National Electricity Market to support AEMO in making accurate demand forecasts and operational decisions. Implementation would be through changes to the National Electricity Rules (NER).

  • Support demand flexibility and co-location with generation through connection agreements: The AEMC has signalled that reforms could also be made to the NERs which govern connection agreements, in relation to:

    • Co-locating with existing renewable generation or firming
    • Connecting with new firming
    • Flexible demand agreements

Changes are expected to be considered by the ECMC in September 2026.

Deeper expectations that data centres bear all network augmentation cost

The Energy Minister, Chris Bowen, has lodged two rule change requests with the AEMC — Cost Recovery for Network Augmentations (Package 1 and Package 2), to amend the NER to ensure data centres pay for network costs they cause or accelerate. The requests address seven identified gaps in the NER. Some of these initiatives are already implemented by network service providers. However, these changes would increase the ability of network service providers to push cost and risk onto data centres. The gaps are as follows:

  • Pricing upstream transmission augmentations into distribution connections: Data centres connecting to the distribution network will be required to pay for the costs of new or accelerated transmission augmentations required to meet their load requirements.
  • Prudential arrangements for asset stranding: Data centres will likely be required to provide prudential support (e.g. bank guarantees, capital contributions, or prepayments) to cover charges for network augmentations at risk of stranding.
  • Safeguards for reallocating the costs of network assets: Networks will be restricted from rolling stranded data centre-funded assets into their regulated asset bases (which are recovered from consumers).
  • Collection, sharing and publication of information on large loads: Improved information requirements for large load connections.
  • Barriers to the use of funded augmentations: Address limitations in the current mechanism to allow applicants to fund upstream transmission augmentations through a "funded augmentation".
  • Jurisdictional scheme costs: Resolve the restriction that jurisdictional scheme costs can only be recovered from distribution-connected customers.
  • Guidelines for transmission connection policies and charges: Introduce guidelines so transmission‑connected data centres are charged for augmentations in line with clear, consistent principles.

NSW system oversight for new load

The NSW Government released the Electricity Infrastructure Investment Amendment Bill 2026 to empower the Minister to control grid access in NSW and require data centres to fund network infrastructure.

There is limited detail on how this scheme will operate, with underlying regulations not yet developed. However, the Bill establishes an ability for the Minister to declare a large load infrastructure access scheme for loads of 5MW or more, enabling the NSW Minister for Energy to control access to specified network infrastructure statewide and introduce a cost‑allocation framework to ensure network upgrade costs for such facilities are not passed on to ordinary NSW electricity consumers.