Joint ventures (JVs) are a central feature of construction across the UAE and the wider GCC. They enable partners in the JV to combine technical expertise, financial strength, and local market access to pursue major developments that individual entities could not undertake alone. For employers contracting with a JV, they provide confidence as a result of the enhanced capability and shared risk.

Notwithstanding the many advantages of joint ventures, they also present inherent challenges, particularly given their long term nature and the likelihood that priorities and positions will change over time. A joint venture compounds the usual pressures of a major construction project by adding additional governance, funding, performance, and strategic risks. Delays, design changes, and commercial strain place significant pressure on joint venture relationships. Where alignment between JV partners falters, disputes can rapidly emerge, with consequential impacts on project delivery. Accordingly, a clear understanding of the causes of such disputes, and the mechanisms for limiting them, is vital for JV participants in the region.

What are JVs and why are they common in the GCC’s construction sector?

A JV enables the parties to collaborate on a construction project while sharing risk and reward. The JV relationship can be either unincorporated or incorporated; we see examples of both in GCC construction projects and each structure has advantages.

Unincorporated JVs are contractual arrangements where the JV parties remain separate entities but use the JV agreement to govern bidding, delivery, and allocation of cost and revenue. They are valued for speed and flexibility, particularly for EPC, building, and infrastructure projects where scope can be divided by discipline. It is worth noting that typically both participants are jointly and severally liable to third parties.

In an incorporated JV, the parties form a special purpose vehicle that contracts directly with the employer. This model suits longer term developments and provides a clearer framework for ownership, governance, and continuity.

JVs are common in the UAE and GCC because local partners offer regulatory familiarity and market access, while international partners bring specialist engineering expertise and project controls. Many major regional projects require combined capability at scale, and government entities frequently prefer structures that pair global expertise with established local delivery.

How JV disputes typically arise in construction projects

It is not uncommon for a construction project to give rise to a dispute even without a JV. When delivery is undertaken by a JV, those disputes may occur both externally with employers and internally between partners regarding responsibility, cost, and strategy.

Internal partner conflicts

Internal partner conflicts strike at the heart of a JV, undermining its ability to act cohesively as a single contracting entity.. Employers expect aligned communication, coherent claims, and unified decision making. When partners diverge, the JV’s negotiating strength and project credibility diminishes.

Many JV agreements promise cooperation between the parties but lack detailed governance. Partners must jointly decide when to notify claims, pursue disputes, approve variations, appoint subcontractors, and allocate budgets. Without clear voting thresholds, escalation routes, and tie break mechanisms, the JV risks delay at critical moments. Deadlock clauses that rely only on senior meetings rarely resolve issues. Effective JV agreements provide defined timelines and ensure continuity while disagreements are escalated.

Performance imbalance is another source of tension. If one partner underperforms, the other may need to step in, reallocate scope, and safeguard delivery. JV agreements therefore benefit from objective performance measures, defined cure periods, and step in rights. Without these tools, dissatisfaction can escalate into damages claims or discussions about termination.

Managing disputes with the employer

Managing disputes with the employer often creates further misalignment. Delay claims require a single narrative, programme analysis, and strong evidence. If JV partners disagree on causation or strategy, the JV’s position weakens. JV agreements should specify how delay positions are formed, who leads claim preparation, and how any internal liability for delay costs, rectification costs, or liquidated damages will be apportioned. A straightforward profit and loss split is generally inadequate. More sophisticated JV agreements therefore tend to allocate responsibilities by reference to defined scopes of work, or apportion liability according to predetermined contractual ratios. Alternatively, the agreement may include a dispute resolution mechanism, such as expert determination, to be used where the JV partners are unable to reach agreement.

External pressures and market‑driven failures

External pressures can also reveal weaknesses in a JV relationship. Material shortages, procurement delays, and price volatility may require revised strategies, and partners may differ on mitigation or cost recoverability. JV agreements should set out principles for mitigation decisions, define when re procurement is required, and allocate additional costs clearly. Where the employer contract offers relief for force majeure or change in law, the JV must act consistently to preserve its entitlement to such relief. JV agreements should include step in rights, the right to assign key subcontracts, mechanisms to secure replacement security, and a fair buy out process. Without these protections, a JV risks severe disruption at a critical point in project delivery.

Reducing the risk of JV disputes in construction projects

Although disputes risk cannot be eliminated, well structured JVs can significantly reduce both the likelihood and impact of a dispute. In addition to the points discussed above, parties entering into JV agreements should keep in mind the following:

  1. Careful due diligence at the outset and careful partner selection: Getting it right at the outset is an investment. Parties should not only assess technical capabilities but also financial strength and viability but cultural and operational compatibility are equally important.
  2. Clear allocation of responsibility: The JV agreement should precisely define work packages, design leadership, key personnel, and responsibility for statutory approvals. Internal allocation should mirror the employer contract so that risk management is aligned. A clear and effective governance structure is important.
  3. Unified claim protocols: The JV agreement should include agreed procedures for early notification, evidence collection, programme analysis, pricing, and approval to reduce internal friction. Costs associated with claim preparation and legal support should be allocated transparently.
  4. Mechanisms for addressing underperformance: Objective benchmarks, cure periods, and step in rights allow the performing partner to maintain project momentum and minimise escalation.
  5. Early involvement of commercial and legal advisers: Experienced advisers can help shape governance structures, align employer risk allocation with internal responsibilities, and develop evidence strategies that support claim entitlement throughout the project lifecycle.
  6. Transparent financial controls: Robust financial procedures reduce mistrust and help prevent disputes relating to spending, reimbursement, and profit allocation. JV agreements should clearly set out budgeting and forecasting processes, approval thresholds, internal audit rights, cost‑sharing mechanisms, and accounting standards.
  7. Clear deadlock and escalation mechanisms: Deadlock is a common trigger for JV failure. The agreement should provide a structured escalation route. Where appropriate, a neutral facilitator or adviser can be built into the process to assist resolution before the dispute becomes entrenched.
  8. Clear default and exit provisions: A well‑drafted JV agreement should define what constitutes a default, the consequences of default, and the process for remedy. Where a partner needs to exit the JV (whether for cause or convenience) the agreement should set out valuation methodologies, buy‑out mechanics, step‑down of obligations, and any continuing liabilities. Clear exit pathways reduce uncertainty at precisely the moment when commercial relationships may already be under strain.
  9. A dispute procedure that is fit for purpose: The dispute resolution clause should reflect the nature, scale, and duration of the project. Multi‑tier mechanisms such as negotiation, senior executive escalation, mediation, and then arbitration or litigation should be clearly defined and realistically sequenced. The clause should also align with the employer contract to avoid parallel or inconsistent proceedings. The governing law, forum, timetable expectations, and rules on interim relief should be set out to provide certainty when disputes arise.

Conclusion

Joint ventures are integral to delivering the region’s most ambitious construction projects. Their success relies on well designed JV agreements that provide for effective governance, clear responsibility allocation, financial transparency, and a coherent commercial strategy. While the goal of “living happily ever after” is aspirational, it can only be achieved through careful planning at the outset and ongoing collaboration during delivery.

With thanks to Jake Burke (Senior Solicitor Apprentice)