Germany’s energy transition is accelerating faster than its grid connection processes can handle. Surging demand for high capacity grid access, driven by the scale up of battery storage and data centers (as well as other loads like electrolysers and industrial sites), has resulted in congestion in connection queues. To give an example, at the end of 2025, the four transmission system operators (TSOs) had received more than 200 GW of battery connection requests alone, which significantly exceeds the assumptions of the current Grid Development Plan.
Recognising that Germany’s electricity system can only be decarbonised at the pace of its grid, the Federal Ministry for Economic Affairs and Energy (Bundesministerium für Wirtschaft und Energie – BMWE) is pursuing a far reaching reform of grid connection law, the grid connection package (Netzanschlusspaket), a draft bill that amends the Energy Industry Act (Energiewirtschaftsgesetz – EnWG) and the Renewable Energy Act (Erneuerbare-Energien-Gesetz – EEG).
In parallel, the four transmission system operators have published a detailed proposal for a maturity-based allocation procedure (Reifegradverfahren), a model that could become the blueprint for managing scarce connection capacity at transmission level.
Together, these initiatives are intended to “break the bottleneck” by creating a transparent, digital, predictable, and readiness driven system across the distribution and transmission grids. At the same time, however, the BMWE draft has triggered sharp criticism, with industry associations warning that the proposed framework could slow down grid expansion, undermine investment signals and ultimately jeopardise the momentum of the Energiewende.
1 The problem: congestion at TSO and DSO level
Across the transmission and distribution grids, connection requests have not only increased, but also changed in character, especially due to more large-scale (data centers, hydrogen production) and more flexible and fast-moving (BESS) assets. The traditional system is struggling to prioritise projects that are actually ready or system-relevant.
1.1 Transmission level congestion
In just two years, TSOs have received more than 200 GW of battery storage requests, far exceeding current grid expansion plans. Large industrial loads, data centers and electrolysers add further pressure. According to the TSOs, capacity for new connections at the high-voltage level is essentially exhausted into the 2030s. Queue management under the traditional Windhundprinzip (“first come, first served”) is no longer fit for purpose. Initially designed for a handful of large power plant connections per year, the system struggles under the weight of hundreds of applications.
1.2 Distribution level congestion
At distribution level, the bottleneck is different but equally binding, considering capacity limits in cables and transformers, voltage constraints and long queues for EV charging hubs, commercial PV, mid-size batteries, and new industrial load. The diversity of DSOs in Germany (roughly 800) means that processes are highly fragmented, with different IT portals, timelines, data requirements and transparency levels.
2 The draft grid connection package: A revised framework for TSO and DSO connections
The draft bill introduces a modernisation of grid connection law for both transmission and distribution grids.
Distribution system operators (DSOs) are required to jointly establish a uniform regime for the reservation of grid connection capacity and its subsequent release. The specific aim is to ensure that applications which are no longer being pursued in earnest do not continue to block grid connection capacity. By 2028, grid operators must publish monthly updated capacity maps, connection timelines, information on planned expansions and standardised datasets via unified portals. This would effectively end the current landscape of fragmented, operator-specific information. Furthermore, grid operators must implement digital self-service portals, standardised templates, automated data interfaces and end-to-end electronic communication.
Meanwhile, TSOs are to be required to establish a modern grid connection procedure that is capable of addressing the challenges arising from new connections of power plants, large-scale battery storage systems and data centers. We have summarized the corresponding TSO concept paper below (see 2.6).
2.1 Reassigning unused grid connection capacity (“Use-it-or-lose-it”)
Until now, once a project received a connection confirmation, capacity could remain tied up for years even if the project failed to progress, contributing significantly to today’s bottlenecks. The new framework aims to change this through a “use‑it‑or‑lose‑it” approach. Connection reservations will no longer be unconditional. Under the new rules grid operators may grant capacity on a conditional basis, requiring project developers to meet defined milestones within specified deadlines and to document project progress in a verifiable manner. This gives grid operators the ability to manage their scarce connection resources dynamically.
2.2 Capacity limited zones (Kapazitätslimitierte Gebiete)
One of the most far‑reaching innovations in the draft grid connection package is the introduction of capacity limited zones (Kapazitätslimitierte Gebiete), geographic zones in which grid connection capacity is officially declared scarce. This creates a new legal category with direct consequences for all grid users. Most importantly, the designation of capacity limited zones interacts directly with several provisions under the EEG. EEG installations traditionally enjoy a “privileged connection right” (Sec. 8 EEG), backed by an obligation on grid operators to expand the grid. In capacity limited zones, however, the unconditional right to immediate connection is temporarily suspended. Furthermore, in capacity limited zones, the draft law allows grid operators to connect new EEG plants only on the basis of a redispatch or curtailment reservation without compensation.
2.3 BESS privileges only for co-location models
According to the draft law, the priority grid connection right pursuant to Section 8 EEG shall not apply to energy storage facilities. However, grid operators may not refuse the connection of energy storage facilities at existing grid connection points by referring to a lack of capacity if the previously prevailing maximum import or export capacity remains unchanged through the additional connection of the storage facility under a flexible grid connection agreement (FCA). The amendment is intended to facilitate the installation of co-located battery storage systems.
2.4 Cost-sharing for renewables: A new era of building cost subsidies?
One of the most controversial elements of the draft grid connection package is the proposal to expand building cost subsidies (Baukostenzuschüsse – BKZ) to renewable generators. Until now, EEG installations have benefitted from a privileged regime: grid operators must optimise, reinforce or expand their grids without charging generators for the structural upgrades required. The draft law departs from this principle and explicitly opens the door for renewable project developers to contribute financially to grid expansion and reinforcement costs. The draft does not specify contribution levels or calculation methodology. Instead, it assigns full regulatory discretion to the Federal Network Agency (Bundesnetzagentur – BNetzA), which would determine the circumstances and formulas under which such contributions apply.
2.5 Introduction of reservation fees
In addition to broader cost‑sharing mechanisms, the draft grid connection package also proposes the introduction of fees for reserving grid connection capacity. Under the draft law, operators may require applicants to pay:
- a non refundable application fee, covering administrative costs, and
- an additional reservation fee, payable when a capacity offer is issued and acting as a financial signal of seriousness.
The exact fee levels are not set in the draft, with the regulatory details delegated to the BNetzA.
2.6 The TSO Reifegradverfahren: A detailed model for transmission level prioritisation
The TSO concept paper presents a proposal for a maturity-based allocation system for TSO level (gleiches Schema wie DSO level) connections of storage and large consumers. Projects are scored across four equally weighted categories:
| Criterion | What is measured? |
| A. Land & permits | Site control, permitting progress, authority engagement |
| B. Technical readiness | Project design, UW concept, detailed routing/trassierung |
| C. Developer capability | Corporate substance, procurement progress, financing |
| D. System value | Hybridisation (e.g., co-location with RE or load), grid benefit |
Up to 18 points can be awarded, with the minimum threshold required for eligibility and additional points determining ranking. After maturity scoring, TSOs assign connection capacity starting with the highest scoring projects. A full network simulation determines whether the requested load is grid compatible. Projects may then receive full, reduced, or no connection in the cycle. Non-successful applicants can roll over into the next round without paying again. The mechanism includes:
- EUR 50,000 application fee (cost covering)
- EUR 1,500/MW realisation bond, deductible from the BKZ and forfeited only if the project fails for developer related reasons
The BMWE draft law creates the legal scaffolding for the TSO model. The proposal anticipates the first application cycle starting in April 2026, with approximately ten months for the first full cycle.
3 What this means for developers, industry and investors
For project developers and financial investors, particularly in the BESS and data center space, the reform package marks a shift in how grid connection opportunities must be approached. When aiming for the connection to the transmission grid, the days in which early‑stage projects could secure grid capacity simply by filing quickly are ending; in the new framework, readiness, financial solidity, technical depth and locational alignment with the grid determine who gains access. This significantly raises the bar for project preparation. Developers will need to secure land, advance permits, contract long‑lead equipment and demonstrate credible financing much earlier than before. This creates a clear competitive advantage for players with existing land holdings or grid connections, potentially to the detriment of smaller developers. Given that by today, approx. 51 GW of BESS capacity has already been awarded on TSO level, there is a need for a transparent and predictable roadmap governing the subsequent connection process.
At the same time, project economics will change. Through the introduction of building cost subsidies for renewable energy installations, the draft signals a shift towards cost‑sharing for grid expansion and reinforcement. Even though the exact methodology remains open, the principle itself alters long‑standing assumptions under the EEG, where grid operators historically bore the full responsibility for reinforcing their grids. When combined with the proposed reservation fees, developers face a more capital‑intensive early phase.
Beyond financial changes, the introduction of capacity limited zones materially affects siting decisions. In these zones, developers may receive reduced or conditional connection offers and must accept curtailment without compensation. This weakens revenue security and will make certain high‑congestion regions less attractive for standalone renewable generation. For asset strategies that depend heavily on predictable feed-in profiles or merchant market optimisation, these conditions increase risk and require more sophisticated modelling, including sensitivity analyses for uncompensated curtailment.
However, it should be noted that the (leaked) draft grid connection package is still at a preliminary stage and may undergo substantial changes before being formally introduced. At this point, no detailed implementation timeline is available.