This article was co-authored with Jack Brown.
Norton Rose Fulbright provides a monthly overview of the key updates to Australian East Coast energy regulation.1 To view our previous instalment, please click here.
| Update | Amended or Governing Instrument(s) | Application | Description | Status |
|---|---|---|---|---|
| Australian Energy Market Commision (AEMC) includes distribution network resilience in the National Electricity Rules2 | Schedule 2 of the National Electricity Amendment (Including distribution network resilience in the National Electricity Rules) Rule 2025 No. 5 | National Electricity Rules –electricity - distribution |
The AEMC has made a final rule to explicitly recognise distribution network resilience in the National Electricity Rules (NER). The final rule will provide regulatory clarity for Distribution Network Service Providers (DNSPs) and the AER on how to assess the economic efficiency of resilience expenditure proposals to reduce the risk and impact on consumers of power outages caused by severe weather events, taking into account the impacts of climate change. The AEMC final rule establishes a formal framework for distribution network resilience in the NER, which includes:
The final rule provides that, from 2 October 2025, the Victorian DNSPs may take the new resilience expenditure factors into account in their revised regulatory proposals for the 2026-31 regulatory control period, and the AER must take the new factors into account in its final distribution determinations. |
The final rule took effect on 2 October 2025. |
| Inter-regional settlements residue arrangements for transmission loops3 | National Electricity Amendment (Inter-regional settlements residue arrangements for transmission loops) Rule 2025 No. 9. | National Electricity Rules –electricity – trading |
On 25 September 2025, the AEMC made a final determination and more preferable final rule that will net off inter-regional settlements residue (IRSR) in transmission loops. This is in response to a rule change request submitted by the AEMO that sought to accommodate the creation of a loop in the NEM once Project EnergyConnect Stage 2 (PEC) is operational. The AEMC consider that a ‘netting off’ approach for allocating IRSR best manages the risks to consumers and keeps costs as low as possible for consumers. Under a “netting off” approach, positive and negative IRSR assigned to each ‘arm’ of the loop in a dispatch interval is pooled together. If the resulting (netted) amount of IRSR is positive, it is distributed to settlements residue distribution (SRD) unit holders, and if it is negative, it is recovered from Coordinating Network Service Providers (CNSPs). Under the final rule:
The final rule does not change the way in which IRSR is distributed for radial interconnectors, for example, the Queensland-NSW interconnector (QNI). |
The final rule came into effect on 2 October 2025. Netting off is scheduled to commence between 1 October 2026 and 2 November 2026. |
| National Electricity (Victoria) (VicGrid) Regulations 2025 (Vic)4 | National Electricity (Victoria) (VicGrid) Regulations 2025 (Vic) | Victoria – electricity |
The Regulations make modifications to the NER. For context, the enabling Act expands VicGrid’s powers to plan, develop, and deliver electricity transmission infrastructure in Victoria as part of Victoria’s renewable energy transition strategy. Previously, VicGrid shared its role with AEMO. Broadly, the Regulations provide the following:
|
The Regulations came into operation on 1 November 2025. |
Footnotes
-
We have curated this list for the key updates. There may be others relevant to your business.
-
AEMC includes distribution network resilience in the National Electricity Rules
-
Inter-regional settlements residue arrangements for transmission loops | AEMC
-
National Electricity (Victoria) (VicGrid) Regulations 2025 | legislation.vic.gov.au