Recent developments in Italy’s renewables framework are likely to have a significant impact on how renewable energy projects are developed, financed and connected to the grid.

On 18 June 2026, the Italian Ministry of Environment and Energy Security (MASE) signed the final FerX Decree, setting out the new incentive framework for eligible renewable energy projects. The FerX Decree builds upon and significantly expands the transitional support mechanism established by the Ministerial Decree of 30 December 2024 (the Transitional FerX Decree). The total incentivised capacity for installations with a capacity exceeding 1 MW is nearly doubled compared to the Transitional FerX Decree, increasing from 14.65 GW to 27.15 GW. The most significant increase concerns wind energy, which rises from 4 GW to 16.5 GW. Allocations for photovoltaic (10 GW), hydroelectric (0.63 GW) and biogas from sewage treatment (0.02 GW) remain unchanged. The Decree will cease to apply on 31 December 2030, or earlier for smaller installations (≤ 1 MW) once the 10 GW threshold is reached.

MASE has also circulated a draft Connections Decree, which introduces a new system for allocating grid capacity for renewable energy plants and storage systems.

Together, the two measures suggest that incentive eligibility and grid capacity will need to be assessed in parallel, rather than as separate stages of project development.

The (definitive) FerX decree: New support scheme

The FerX Decree applies to solar photovoltaic installations, including agrivoltaic systems and floating systems, wind energy, hydroelectric plants, and biogas installations from sewage treatment processes. The FerX Decree was approved by the European Commission on 8 June 2026, confirming its compatibility with EU State aid rules.

The key features for developers and investors may be summarised as follows:

Access requirements and competitive procedures

The FerX Decree establishes two distinct access mechanisms:

  • Installations with a capacity of up to 1 MW may access the support mechanism directly upon entering into operation, without the need to participate in competitive tenders.
  • Installations exceeding 1 MW must participate in competitive auctions organised by the GSE and require: (i) a valid construction and operation permit (including concession titles, where applicable, while a positive environmental impact assessment is no longer sufficient, unlike under the Transitional FerX Decree); (ii) an accepted grid connection proposal validated by Terna’s GAUDI system; (iii) compliance with the “Do No Significant Harm” (DNSH) principle; and (iv) mandatory participation in the Balancing and Redispatching Market. Financial soundness must also be demonstrated through either a bank declaration confirming financial capacity or adequate capitalisation thresholds (10% for investments up to EUR 100 million, 5% between EUR 100 million and EUR 200 million, and 2% for amounts exceeding EUR 200 million).

Procedural timelines have also been significantly shortened compared with the Transitional FerX Decree: the window for submitting participation requests has been reduced from 60 days to a maximum of 10 days, and rankings must be published within 10 working days, compared with 90 days under the transitional regime. A preliminary qualification is also now required to confirm compliance with the access requirements before any expression of interest.

Reference prices and auction mechanism

The table below sets out the three price parameters by technology. The Reference Price is the auction base price from which participants must offer reductions to secure a contract. The Upper Reference Price sets the ceiling above which the award price cannot rise, while the Lower Reference Price sets the floor below which no bid may be submitted. The final award price, determined by the winning bid, becomes the contractual reference for the two-way contract for difference with the GSE over the 20-year support period.

Photovoltaic Wind Energy Hydroelectric Biogas installations from sewage treatment processes
Reference price 80 €/MWh 85 €/MWh 90 €/MWh 85 €/MWh
Upper Reference Price 95 €/MWh 95 €/MWh 105 €/MWh 100 €/MWh
Lower Reference Price 65 €/MWh 70 €/MWh 80 €/MWh 75 €/MWh

Locational coefficients

The FerX Decree introduces differentiated locational coefficients by market zone, to be applied to reduction bids submitted in competitive procedures for ranking purposes. The aim is to incentivise installations in areas where additional renewable capacity is most needed, while penalising those in already congested zones.

Such coefficients will be defined by MASE, with technical support from Terna and the GSE, within 60 days of the FerX Decree’s publication.

Two-way contracts for difference

For all installations with a capacity exceeding 1 MW, participation in Terna’s Balancing and Dispatching Market becomes mandatory, and support is provided exclusively through two-way contracts for difference. The producer receives a payment when the market price falls below the award price and repays the difference where the market price exceeds it. This mechanism applies to 95% of the energy produced, leaving a degree of commercial flexibility for the remaining 5% (for example, merchant or PPA arrangements).

For installations of up to 200 kW, the GSE directly withdraws and sells the electricity, paying the award price as an all-inclusive tariff. For installations of 200 kW or more, the producer retains commercial control over the energy and settles differences with the GSE based on the Day-Ahead Market price.

Duration of support and price indexation

The support mechanism runs for 20 years from the date of entry into operation and includes a more comprehensive inflation indexation mechanism. Award prices are indexed to inflation using the national consumer price index, with adjustments applied both at entry into operation (based on inflation between the tender publication date and expected entry into operation) and annually during the contract term (applied to the portion of the price covering operating and maintenance costs, differentiated by technology).

Commissioning

Installation Type Intervention Category Months
Wind Energy All eligible interventions 36
Solar Photovoltaic All eligible interventions 36
Hydroelectric New constructions 54
Biogas installations from sewage treatment processes New constructions/Upgrades 48
Hydroelectric Repowering 48
Biogas installations from sewage treatment processes Repowering 36

Failure to comply with the deadlines set out in the table above shall result in a reduction of the award price of 0.2% per month of delay for the first nine months, and 0.5% for the subsequent six months, up to a maximum of fifteen months.

Following the maximum 15-month extension, failure to commission the plant results in exclusion from the ranking and forfeiture of the definitive guarantee. If the project is subsequently readmitted to a support mechanism, a further 5% reduction of the award price will apply.

Guarantees and caution deposits

Participants in competitive procedures must post a provisional guarantee equal to 5% of the investment cost, calculated using the specific investment costs in the FerX Decree: EUR 900/kW for photovoltaic, EUR 1,420/kW for wind, EUR 3,160/kW for hydroelectric and EUR 3,500/kW for biogas from sewage treatment. Upon successful admission to the ranking, a definitive guarantee of 10% of the investment cost must be posted within 30 days. Early withdrawal from a successful bid results in partial forfeiture: 30% if notified within six months of publication of the ranking, and 50% if notified between six and twelve months.

Cumulation with other incentives

The FerX support mechanism may be cumulated with: (i) capital grants not exceeding 40% of the investment cost (for new installations only); (ii) guarantee funds and revolving funds; and (iii) tax incentives in the form of tax credits or income deductions for investments in machinery and equipment. Where a capital grant is received, the award price is reduced proportionally (with a factor ranging from 0 to 35% depending on the grant level). The mechanism is, however, alternative to the net metering scheme and the dedicated withdrawal regime.

Special provisions for asbestos replacement and floating photovoltaic

The Decree provides for upward adjustments to the award price in certain cases: +27 EUR/MWh for photovoltaic installations replacing roofing containing asbestos or Eternit (with complete removal required), and +10 EUR/MWh for floating photovoltaic installations (increased from +5 EUR/MWh under the Transitional FerX Decree).

Net-Zero Industry Act procedures

The Decree also implements the Net-Zero Industry Act (Regulation (EU) 2024/1735) by reserving at least 30% of annual capacity for photovoltaic and wind installations to dedicated procedures applying additional pre-selection and award criteria. These include responsible business conduct, cybersecurity and data protection requirements, the ability to complete the project on time, and contribution to resilience, relating to the origin of final products and key components. Compliance with sustainability criteria, such as the integration of storage systems with at least 25% of the installation’s nominal capacity, is also assessed.

The draft connections decree: A new grid access model

The draft Connections Decree implements Article 7(2) of DL No. 21/2026 (DL Bollette) and sets out a new framework for access to the National Transmission Grid for renewable energy plants and storage systems, excluding offshore projects.

The decree remains in draft form and has not yet entered into force. Based on the version currently available, it will become effective on the day after publication on MASE’s website, while several key operational aspects — including the detailed rules for the Open Season process — will be defined by the Italian Regulatory Authority for Energy, Networks and Environment (ARERA).

Capacity allocation through open season

The draft decree introduces an Open Season model for grid connections.

Available capacity will be allocated by reference to “Microzones”, i.e. regional or sub-regional portions of the National Transmission Grid (NTG) intended to reflect the main technical constraints affecting electricity transmission within each market area. Terna will be required to update these Microzones at least every two years and to make available connection capacity equal to at least 150% of the capacity targets set out in Annex C-bis to Legislative Decree No. 190/2024, net of the capacity expected to be connected to distribution grids.

Under the Open Season process, Terna will publish an offer on the so-called Terna Portal before each session, indicating the available connection points, the relevant capacity and the status of the associated grid works. Applicants will then be able to select a minimum technical connection solution and obtain an “attestation” (attestazione).

The attestation does not, by itself, reserve grid capacity. It allows the applicant to proceed with the permitting procedure, but capacity is effectively secured only when the attestation gives rise to a “grid capacity reserve”. This occurs once the applicant notifies Terna that the relevant permitting procedure has been completed. Where Terna issues connection solutions in excess of the available capacity or connection points, priority for the grid capacity reserve will depend on the chronological order in which applicants notify Terna that the relevant permit has been granted.

Pending projects

The transitional regime will be particularly relevant for projects already in development. Within 15 days of publication of ARERA’s implementing measures, Terna must notify applicants and the competent authorities where existing connection solutions to the NTG lose effectiveness. Certain solutions will remain effective, including those relating to grid works whose technical plan has already been validated by Terna, or to grid works that have already been authorised or already exist.

Projects that have already obtained an exemption from, or a positive, environmental impact assessment will also need to notify Terna within the relevant 15-day period. Terna will then assess whether the related grid works may be included in the offer.

The draft decree also addresses cases of supervening grid saturation. Where saturation arises while the permitting process is still pending, the procedure is suspended to allow the connection solution to be adjusted. Where the authorisation has already been issued, the amendments should follow a simplified or priority authorisation route.

Why these decrees matter

Read together, the FerX Decree and the draft Connections Decree point in the same direction: renewable projects increasingly need to be assessed not only by tariff levels, but also by location, grid availability and permitting timetable. The FerX Decree introduces stronger signals on where new capacity should be developed and how projects will interact with the electricity market.

The draft Connections Decree, in turn, makes clear that grid capacity may depend on the timely conversion of an attestation into a grid capacity reserve. For developers and investors, this means that a project’s economic viability will increasingly depend on how effectively its incentive structure, permitting timeline and grid connection strategy are aligned from the beginning.