As British Columbia’s new prompt payment legislation moves closer to implementation, understanding how the Construction Prompt Payment Act will affect payment timelines, disputes, and suspension rights is crucial for construction industry participants. Introduced through Bill 20 and passed on November 27, 2025, the Act is modeled on similar frameworks in place in other Canadian jurisdictions and will significantly change how owners, contractors, and subcontractors invoice, pay, challenge payment, and resolve disputes on construction projects.

Once in force, the Act will apply to contracts for the supply of services or materials for a construction improvement, subject to any regulations passed to exempt a specific improvement, contract, service, or material. The Act will apply to contracts and related subcontracts made on or after the legislation comes into force. Contracts already signed will not be affected, even if they continue after the Act takes effect.

On June 4, 2026, the Ministry of Infrastructure released a discussion paper seeking feedback from industry participants on key regulatory topics, including the scope of application and coming into force of the Act, calculation of days, interest rates on late payments, adjudicator qualifications and fees, and industry readiness and support. Written submissions in response to the discussion paper are being accepted until July 7, 2026. The discussion paper is available here.

Key takeaways

For contracts to which the Act applies:

  • Owners must pay contractors within 28 days of the invoice date, regardless of longer payment periods as may be specified in contracts.
  • Payment obligations are triggered by “proper invoices,” which may not be delayed by payment certification or approval requirements.
  • Strict notice of non‑payment rules apply, with tight statutory deadlines and prescribed content.
  • Payment disputes may be referred to adjudication at any time during a project, even if litigation or arbitration is underway.
  • Unpaid parties gain a statutory right to suspend work if adjudicated amounts are not paid within 15 days.
  • Interest is charged on late payments at the higher of the rate set out in regulations or the rate (if any) set out in the contract.

Prompt payment and invoices

Under the Act, payment obligations are triggered by delivery of a “proper invoice.” An invoice is deemed to be a proper invoice unless, within seven days of the invoice date, the owner gives a notice identifying a non-conformance with proper invoice requirements. Owners must pay contractors within 28 days of the invoice date of a proper invoice. Contractors and subcontractors must pass payment down the chain within seven days of receiving payment, or by a “calculated payment date,” which adds seven days for each contractual tier below the owner.

Contracts can no longer require certification or owner approval before a proper invoice is issued. Consultant review and certification may still occur, but only after the invoice has been delivered. Accordingly, invoice delivery, not certification, starts the payment clock. Owners and consultants will need to adjust internal payment and review processes to avoid missed deadlines.

Non-payment notices

The Act establishes a mandatory notice of non payment regime. An owner disputing a proper invoice must deliver a written notice of non payment within 14 days of the invoice date, identifying the amount not being paid and the reasons for non payment. Contractors and subcontractors face similarly tight downstream notice timelines.

Where non payment is based on non payment higher in the contractual chain, the notice must include an undertaking to refer the matter to adjudication.

Interest on late payments

Interest accrues on late payments, being amounts not paid within the required prompt payment timelines or within 15 days of an adjudicator’s determination, at the higher of the rate prescribed by regulation (expected to be tied to the pre-judgement interest rate published by the Registrar to the Supreme Court of British Columbia, currently 2.45%) or the rate (if any) set out in the contract.

Adjudication and enforcement

The Act introduces a fast track adjudication process for payment related disputes, including valuation and change order disputes. Adjudication may be commenced at any time during a construction project, subject to a 90-day limitation period, the commencement of which differs for head contracts versus subcontracts. A dispute may be referred to adjudication even if the dispute is also the subject of a court proceeding or arbitration, and adjudication determinations cannot be stayed pending those proceedings.

Adjudicators are generally required to issue a written determination within 30 days of receiving the parties’ records. Determinations are binding on the parties on an interim basis, and any amount ordered to be paid must be paid within 15 days.

If payment is not made, the unpaid party may suspend work under the contract without breaching it and may recover interest costs together with reasonable costs incurred from the suspension and resumption of work.

The Act allows for an adjudicator’s decision to be judicially reviewed on limited grounds specified in the Act. An application for judicial review of a determination must be made within 35 days after the determination is issued.

Consistent with the approach taken in other Canadian jurisdictions, adjudicators in British Columbia are expected to be required to have a minimum of 10 years of relevant construction industry experience, complete required training, and meet basic eligibility requirements such as not being an undischarged bankrupt or having been convicted of an indictable offence. Adjudication fees are expected to be based on the amount in dispute rather than the total contract value, with fee caps commonly applied to lower-value disputes (often those under C$50,000), while higher-value disputes generally have no fixed fee ceiling and rely on agreement with the adjudicator.

Amendments to Builders Lien Act

The Act includes some important amendments to the Builders Lien Act, S.B.C. 1997, c. 45, including reducing the holdback release period from 55 days to 46 days, and confirming that no lien exists against a statutory holdback itself, thus abolishing the controversial so called Shimco liens.

Preparing for implementation

The Act will come into force on a date to be set via regulation. Before then, owners, contractors, subcontractors and service providers should consider taking the following steps to prepare:

  1. Reviewing the government discussion paper and providing feedback regarding the consultation questions.
  2. Reviewing contract templates, payment workflows, and dispute management strategies and considering changes needed for alignment with the Act’s prompt payment, notice, and adjudication requirements.

The authors would like to thank Allan Hsu, articling student, for his contribution to preparing this legal update.

Contact