As of January 1, 2026, long-awaited changes to Ontario’s Construction Act (the Act) are now in force. The amendments were introduced to address certain “pain points” with the prompt payment and adjudication scheme, now that it is a few years old, and to modernize other parts of the legislation1 In our previous update, we discussed the new mandatory annual holdback release requirements, expanded prohibitions on the use of holdback following contract termination or abandonment, and transitional rules for P3 agreements.

Changes to “proper invoice” and “price”

Prompt payment obligations in the Act are triggered by submission of a “proper invoice,” which is a defined term in the legislation. Much ink has been spilled by adjudicators on what counts as a “proper invoice” and how strictly the statutory requirements need to be complied with.

The recent changes aim to further the Act’s objective of streamlining the payment process by minimizing delays caused by disputed invoices.

First, the definition of a “proper invoice” under Section 6.1(1) of the Act has now been updated to reflect practical project requirements, specifying that a proper invoice must include “any other information that is necessary for the proper functioning of the owner’s accounts payable system that the owner reasonably requests.” We expect any information of this nature that an owner requires will be spelled out in tender and contract documents.

However, in theory, an owner may “request” additional information mid-project and contractors hoping to trigger the prompt payment provisions with their payment applications will need to comply, assuming that the request is “reasonable” (which could lead to additional interpretation disputes).

Second, and more significantly, the Act now includes a “deemed proper invoice rule.”2 An invoice that does not meet the formal requirements will still be deemed “proper,” triggering prompt payment timelines, unless the owner notifies the contractor of deficiencies within seven days of receiving the otherwise improper invoice. Owners will need to pay close attention to whether a contractor’s invoice is “proper” once received, and, arguably, it may also lead to further paperwork and real-time disputes over invoicing.

Adjudication regime overhaul

In 2024, we published an update discussing the significant changes Bill 216 proposed to Ontario’s adjudication regime, and most of them made it into the final amended version of the legislation we have today.3 Key changes include:

  • Introduction of a 90-day deadline to commence adjudication after contract completion, termination or abandonment.4

Additional changes first introduced in 2025 by O Reg 264/25, also effective January 1, 2026, further expand the availability of adjudication.

Previously, the Act allowed adjudication only for predominantly payment-related issues, unless the parties could agree to broaden the scope of issues to be adjudicated. Now, the types of issues that can be brought to an adjudicator have expanded to include:

  • The scope of work required to be performed under the contract.
  • A request for a change in the contract price.
  • A request for an extension of time in the completion of work required to be performed under the contract.10

Parties are now also expressly permitted to choose a private adjudicator, rather than one of the ODACC adjudicators, so long that the individual has completed ODACC qualification/training.11 However, parties are still incentivized to use ODACC’s adjudicator registry because the Act has set a minimum hourly rate for private adjudicators of $1,000/hr (whereas the ODACC registry offers adjudicators with hourly rates lower than this).12

Introduction of contract termination notice deadlines

The Act now imposes new obligations in situations where a contract has been terminated (being the contract between the “owner” and “contractor” under the Act), aimed at ensuring that any party whose lien period might be triggered as a result receives proper notice:

  • The owner, contractor, “or other person whose lien is subject to expiry” must publish a notice of termination (Form 8) no later than seven days after the contract is terminated.13
  • The publication of Form 8 shall be on one of the three stipulated construction trade news websites: The Daily Commercial News, Link2Build, or  Ontario Construction News.14
  • The date of termination for the purposes of triggering lien periods to run will be deemed to be the date on which the first notice of termination was published (where more than one notice is published).15
  • The deemed date of termination does not prohibit any party from contesting the validity of the termination.16

The key takeaways are that contractors and owners must ensure their notices of termination are published within the prescribed seven-day window, and subcontractors/suppliers should regularly monitor the major trade publication sites for termination notices to ensure liens are preserved within prescribed timelines (much like monitoring for a Certificate of Substantial Performance to be published).

Conclusion

Given these and other significant amendments, now is the time for construction stakeholders to review their contracts and operational procedures to ensure alignment with the new requirements, and to educate project teams so those facilitating contracts and subcontracts are familiar with the changes.

The author would like to thank Matteo LeClair, articling student, for his contribution to preparing this legal update.

Footnotes

  1. 1

    The amendments were first introduced by bills passed in the Ontario legislature: Building Ontario For You Act (Budget Measures), 2024, S.O. 2024, c. 20 (Bill 216) Fighting Delays and the Building Faster Act, 2025, S.O. 2025, c. 14 (Bill 60).

  2. 2

    Act, s. 6.1(2).

  3. 3

    Bill 60 does strike out the words “responsible for the administration of this Act” from subsections 13.2(1), 13.4(1), and 13.4(2) of the Construction Act which pertain to adjudication. These changes are minimal, and do not impact the substance of the Bill 216 amendments.

  4. 4

    Act, s. 13.5(3) and (3.1).

  5. 5

    O. Reg. 264/25: Adjudications Under Part II.1 of the Act, s. 16.

  6. 6

    Act, s. 13.12.1.

  7. 7

    Act, s. 13.7(e).

  8. 8

    Act, s. 13.7.1.

  9. 9

    Act, s. 13.8(2); see also O. Reg. 264/25, s. 26.

  10. 10

    O. Reg. 264/25, s. 19(1)6.

  11. 11

    Act, s. 13.9(2.1); see also O. Reg 264/25, s. 21.

  12. 12

    O. Reg. 264/25, s. 21(b).

  13. 13

    Act, s. 31(6).

  14. 14

    O. Reg. 304/18: General, s. 1.

  15. 15

    Act, s. 31(7).

  16. 16

    Act, s. 31(8).

Contact