Three consultation papers have been released addressing the next tranche of reforms to the Environment Protection and Biodiversity Conservation Act 1999 (Cth) (EPBC Act), proposed to commence on 1 July 2026. The papers address the establishment of the National Environmental Protection Agency (National EPA), the statutory head of Environment Information Australia (EIA), and the early commencement of several significant new regulatory powers and provisions under the Environment Protection Reform Act 2025 (Cth) (EPBC Reform Act). The consultation period closes on 21 May 2026.

Highlights

  • As we reported previously, the federal environment protection reforms are commencing in stages. The Commonwealth Department of Climate Change, Energy, the Environment and Water (DCCEEW) is now consulting on the reforms, regulations and rules proposed to commence on 1 July 2026.
  • In particular, DCCEEW is consulting on new regulations and rules supporting the commencement of the National EPA on 1 July 2026, including early commencement of its new powers to support its effective operation.
  • DCCEEW is also proposing to bring forward to 1 July 2026 the commencement of provisions relating to protection statements, rulings, the unacceptable impact definition, minor or preparatory works, reconsiderations and lapsing of not controlled action decisions. The papers set out additional detail about regulations proposed to support these changes.
  • Finally, DCCEEW is consulting on bilateral agreements and new substantive tests for those agreements. Again, DCCEEW is proposing to bring forward the start date of these changes to 1 July 2026, along with supporting regulations.
  • This is the first time that several of these reforms have been identified for early commencement. These changes may impact project planning, and proponents should carefully consider the papers and prepare submissions as appropriate.

Consultation papers

The three consultation papers address the provisions of the EPBC Act commencing on 1 July 2026 and the subordinate legislation required to give effect to those provisions.

Consultation Paper 1: A smooth transition to the National EPA

This paper explains the supporting regulations and rules, and early commencement of new powers to support the operation of the National EPA. Key takeaways include:

New powers

  • The National EPA will be overseen by a Chief Executive Officer (CEO).
  • The National EPA will have the power to issue environment protection orders or ‘stop work orders’ where there is an imminent risk of serious damage to the environment.
  • Some existing powers currently exercised by the Minister and the Secretary of the Department of Climate Change, the Environment and Water will be transferred to the CEO.1
  • The CEO will also be able to make rulings on how the EPBC Act, subordinate legislation and National Environmental Standards should be applied.

New audit arrangements

  • Reformed environmental audits will be able to be carried out in relation to all approvals, orders, exemptions or other permissions under the EPBC Act.
  • The reforms expand ‘directed environmental audits’ and introduce new ‘compliance audits’ to monitor compliance under the EPBC Act, together with a framework for auditor registration.

Transparency rules

  • The National EPA will publish certain regulatory decisions and compliance outcomes on public electronic registers.
  • Proposed rules will specify which CEO decisions must appear on these registers and prescribe additional information (including enforcement actions, civil penalty orders, and injunctions) that must be published.

Consultation Paper 2: More certainty for projects and environment protection

This paper provides details around how decision-making under the amended EPBC Act will work.

Key takeaways include:

Protection Statements

  • Protection Statements will be able to be issued by the Minister, including information relevant to assessing impacts on listed threatened species or ecological communities.
  • Once made, they must be considered by decision-makers in approval decisions, including when making bilateral and accredited agreements and bioregional plans.
  • Protection Statements combine and clarify aspects of Recovery Plans, Conservation Advice and policies to guide decision-making.

Rulings

  • The Minister and the CEO will have the power to make ‘rulings’ under new Part 19C of the EPBC Act.
  • Rulings are formal opinions on how the law, regulations or National Environment Standards should be applied in specific situations and are intended to provide clarity for proponents navigating the reformed EPBC Act.
  • Decision-makers must generally act consistently with any rulings. If they do not, they must publish reasons for the inconsistency.

Unacceptable impact definition

  • The EPBC Act will include legislated criteria defining what constitutes an ‘unacceptable impact’ for each protected matter. The new definition will apply to referral decisions and (once the balance of the reforms commence later in 2026) approval decisions.
  • If the Minister determines that an impact is unacceptable, it must be avoided and cannot be offset, unless the action is a national interest proposal.

Minor preparatory works

  • Proponents with controlled action decisions under assessment will be able to seek the Minister’s agreement for ‘minor’ or ‘preparatory’ works while awaiting an approval decision.
  • The Minister must determine whether to agree within 20 business days of receiving a complete application. The primary test is whether the works are ‘minor and repairable’ to matters protected under Part 3 of the EPBC Act.
  • This provision offers meaningful flexibility for proponents facing delays in the assessment process and will be available for any controlled action currently under assessment.

Reconsideration and lapsing of ‘not a controlled action’ decisions

  • The amendments will streamline the process for the Minister to reconsider decisions that a project is or is not a controlled action, where new substantial information arises or circumstances change significantly.
  • The reforms introduce a new power for the Minister to lapse a decision that an action is ‘not controlled action’ (including if carried out in a ‘particular manner’) that have not substantially commenced after five years from the initial decision.2
  • The lapsing regime will apply only to decisions made on or after 1 July 2026. Proponents nearing referral should factor these new time limits into their project planning.

Consultation Paper 3: Reducing duplication

The reforms commencing on 1 July 2026 are also directed at improving the process for the Minister to recognise State, Territory and Commonwealth regulatory processes.

Bilateral agreements and Commonwealth accreditation

  • The reforms introduce new legislative tests that new or varied bilateral agreements and Commonwealth accreditation declarations must satisfy.
  • The CEO must review bilateral agreements after three years and every five years thereafter.
  • The CEO can conduct assurance reviews at any time.

NOPSEMA declaration

  • The reforms give the Minister a new power to declare that certain offshore petroleum and greenhouse gas activities do not need separate EPBC Act approval where they are covered by the Offshore Petroleum and Greenhouse Gas Storage (Environment) Regulations 2023.
  • Before making such a declaration, the Minister must be satisfied that NOPSEMA’s framework meets a range of requirements including consistency with National Environmental Standards.
  • Commencement of this power on 1 July 2026 will allow the assessment of NOPSEMA’s framework to proceed.

Greenhouse gas emission reporting

  • The reforms introduce a requirement for proponents over a specified threshold to disclose a reasonable estimate of scope 1 and scope 2 greenhouse gas emissions, along with management strategies.
  • The proposed threshold aligns with the National Greenhouse and Energy Reporting (Safeguard Mechanism) Rule 2015 (Cth). This is currently 100,000 tonnes of CO2-e per year.
  • The reporting requirement will not apply to single projects until the assessment pathway changes commence later in 2026.

What to consider as 1 July 2026 approaches

The new framework governing the National EPA should be a central consideration for all holders of EPBC Act approvals in their operational phase.

From 1 July 2026, the regulatory environment is likely to undergo a fundamental shift to place heavy emphasis on compliance.

For proponents of projects, the reformed assessment and approval regime continues to take shape in the near future, which may influence project planning.

What’s next?

Consultations on the National EPA subordinate legislation closed on 21 May 2026. More information on the Consultation Papers can be found here.

The full suite of reforms is required to commence by 1 December 2026; however, the Government may seek to bring forward another tranche before the end of the year.

We anticipate further consultations on key aspects of the remaining reforms, including the Restoration Contributions Holder scheme, in the latter half of the year.

Footnotes

  1. 1

    EPBC Reform Act Schedule 2

  2. 2

    EPBC Act section 75; EPBC Reform Act s 79F

card-grid-item, aem-sourced
Federal environment reforms
As the reforms progress, we’ll share our analysis and practical updates to help you navigate the potential impacts on your business and projects.
/content/nrf-eds/en-au/topics/federal-environment-reforms

Contact